The estimated duration of this phase is 42 hours. During the final preparation phase, the following team members are required.

 

Team member

Estimated Time Commitment

SAP Business One Project Manager

4 hours

SAP Business One Consultant

42 hours

Client Project Manager

18 hours

Client IT Administrator

25 hours

Client LeadAccounting

18 hours

Client LeadSales

18 hours

Client LeadOperations

18 hours

Client LeadPurchasing

18 hours

Client LeadLogistics

18 hours

Client Lead - HR

18 hours

 

The SAP Business One project manager and the SAP Business One consultants are responsible for scheduling and conducting user and administrator training. Training schedules and execution are supported by the client project manager and, from an infrastructure perspective, by the client IT administrator. Client functional leads and end users need to attend the relevant training.

 

System readiness checks need to be completed by the SAP Business One consultants and the client IT administrator. SAP Business One project manager and consultants as well as all client team members are responsible for the thorough completion of all cut-over activities.